The current phase in North House Project A180 involves backfilling works for reinforced foundations. Suitable backfill materials are being used, and the soil is being prepared and compacted to ensure solid and effective foundation support. This process is a critical step toward advancing construction phases and establishing the structural framework

Project Status: Under Construction
Project district: North House
Project Type: Residential,apartment
Project delivery: 2025-06-30
Number of floors: 4
space available: M
Concrete structure
5 %
Interior finishes
0 %
Facade finishes and entrances
0 %

Overall Progress