The construction of all floors in the project has been completed, including the foundations, structural framework, and initial finishes. Currently, we are in the final phase of interior finishes, and work is ongoing to prepare the units for handover within the scheduled timeframe.

Project Status: Under Construction
Project district: South Suez Area in the Fifth Settlement
Project Type: Residential,apartment
Project delivery: 2025-09-30
Number of floors: 4
space available: 160M-145 M
Concrete structure
100 %
Interior finishes
0 %
Facade finishes and entrances
100 %

Overall Progress

Tags : South Suez Project Construction Work D156 Construction Floors